Skip to main content
European Commission logo
TRIMIS

Optimised Procedures and Techniques for Improvement of Approach and Landing

PROJECTS
Funding
European
European Union
Duration
-
Status
Complete with results
Geo-spatial type
Other
Total project cost
€42 293 707
EU Contribution
€21 991 855
Project website
Project Acronym
OPTIMAL
STRIA Roadmaps
Vehicle design and manufacturing (VDM)
Network and traffic management systems (NTM)
Transport mode
Airborne icon
Transport policies
Digitalisation,
Safety/Security
Transport sectors
Passenger transport,
Freight transport

Overview

Call for proposal
FP6-2002-AERO-1
Link to CORDIS
Background & Policy context

The major airports are increasingly capacity constrained, resulting in significant delays causing frustration and difficulties for both passengers and aircraft operators, and causing environmental problems. The compounded effects of more movements over longer periods of the day and night have increased the disturbance. This has fuelled the resistance of the population living near an airport against further expansion of the facility and its operations.

Objectives

OPTIMAL was an air-ground cooperative project, which aimed at defining and validating innovative procedures for the approach and landing phases of aircraft and rotorcraft. The objective was to increase airport capacity and to reduce environmental impacts (noise and carbon footprints) while maintaining or even improving operational safety.

The work packages objectives were the following:

WP0: Project management & dissemination work package: this work-package consisted in managing the consortium and ensuring the reporting to the Commission and the technical coordination with the partners. In addition this work package ensured the dissemination activities.

WP1: Operational concept work package: this work-package elaborated the operational concepts for pilots and controllers so that target objectives in terms of capacity, safety and environment are met in the time frame 2010-2020. The qualitative benefits of selected approach and landing procedures were identified.

WP2: Procedures definition, development & design work package: this work package produced the design and the detailed specifications of the selected procedures and allocated the operational requirements to airborne (aircraft or rotorcraft) and to ground segments. After development of the generic procedures for aircraft and rotorcraft, some procedures for specific airports have been developed for tests purpose. In this WP, a specific study related to flight dynamics aspects of rotorcraft SNI operations has been carried out.

Aircraft (WP3), Rotorcraft (WP4) and Ground functions (WP5) developments: these three work-packages were conducted in parallel in order to implement the necessary airborne and ground functions to fly the new or improved approach procedures developed in WP2. Furthermore, where necessary, platforms were modified for the flight trials and for the manned simulations carried out in WP7.

WP6: The Validation & Conclusion: This work package prepared and coordinated the Validation Framework that guided the exercises. More specifically, it developed the validation strategy followed by the validation exercise plan, it conducted the analysis of the performance benefit assessment test results and elaborated the overall conclusion from all exercise results.

WP7: Exercise management & Support: in this WP, tests to assess the performances of the OPTIMAL procedures were carried out. The objective was twofold: it aimed at demonstrating the b

Methodology

Two validation techniques were applied in the OPTIMAL validation process:

  • Fast Time Techniques were suitable for a preliminary assessment of the benefits of a new concept in the ATM environment using a mathematical model to provide the results of the simulation and has rules defined to represent the relationship between the different actors of the validation scenario. They consisted in analytical studies applied for safety, environmental and economic assessments and Fast Time Simulation applied for the capacity assessments.
  • Real Time Techniques were characterized by the presence of one or more subject matter expert as controllers or pilots that perform their operational tasks in a realistic real-time environment. Real time techniques are generally used for assessing the human factors aspects, but also to validate the interoperability between systems. In the OPTIMAL validation process, Real Time Simulation and Flight trials were applied as Real Time Techniques.

Two types of exercises ensured the consistency of the overall validation process:

  • Benefit assessments assessed the benefits obtained from the implementation of the new procedures according to the high-level objectives capacity, environment and safety.
  • Feasibility assessments evaluated specific functions for airborne and ground systems and include the validation of flyability requirements, operational requirements (both for pilot and controller), air-ground interoperability requirements and systems performance requirements.

Funding

Parent Programmes
Institution Type
Public institution
Institution Name
European Commission
Type of funding
Public (EU)

Results

The OPTIMAL project successfully ended on the 31st of October 2008. The following global conclusions can be drawn:

  • All main activities in terms of studies, developments and tests defined in the initial contract were carried out in the frame of the project, albeit with a slight delay.
  • All project objectives were met and OPTIMAL demonstrated that the studied procedures provide in general the expected benefits in terms of capacity, safety and/or environmental impact and that the procedures are feasible.
  • The OPTIMAL results were disseminated during the whole duration of the project, especially through the successful final user forum in June 2008.
  • All OPTIMAL partners acknowledge the very good and fruitful cooperation within the consortium and the management team thanks the 24 partners for their involvement and their cooperative spirit to meet the project objectives.
  • To conclude, the OPTIMAL project delivered some validated, innovative concepts and promising results, which will certainly contribute to the SESAR JU and the implementation of the future European ATM system.

Technical Implications

The work conducted during the project implementation ranged from the elaboration of the operational concept to simulations and pre-operational flight trials implying effective modifications of avionics onboard aircraft and rotorcraft and ground systems. On the ground system side special attention was placed on the new tools, which were necessary for Air Traffic Controller to efficiently and safely manage the OPTIMAL procedures.

Readiness

The target time frame for the operational implementation of the OPTIMAL proposed procedures is 2010 and beyond. OPTIMAL has therefore delivered an important contribution to the targets for airport capacity development identified in the ATM +2000 Strategy.

Partners

Lead Organisation
Organisation
Airbus Operations Sas
Address
ROUTE DE BAYONNE 316, 31060 TOULOUSE, France
Organisation website
Partner Organisations
Organisation
Thales Avionics
Address
1 avenue Carnot, MASSY, France
Organisation website
EU Contribution
€0
Organisation
Eurocontrol - European Organisation For The Safety Of Air Navigation
Address
Rue De La Fusée 96, 1130 Bruxelles, Belgium
EU Contribution
€0
Organisation
The University Of Liverpool
Address
Senate House, Abercromby Square, LIVERPOOL, United Kingdom
Organisation website
EU Contribution
€0
Organisation
Eurocopter
Address
Aéroport International Marseille-Provence, BP 13 MARIGNANE, France
Organisation website
EU Contribution
€0
Organisation
Stichting Centrum Voor De Ontwikkeling Van Transport En Logistiek In Europa
Address
Van Nelleweg 1, 3044 BC Rotterdam, Netherlands
Organisation website
EU Contribution
€0
Organisation
Dfs Deutsche Flugsicherung Gmbh
Address
Am DFS-Campus 10, 63225 LANGEN, Germany
Organisation website
EU Contribution
€0
Organisation
Airbus
Address
2 ROND POINT EMILE DEWOITINE, 31700 BLAGNAC, France
Organisation website
EU Contribution
€0
Organisation
Deutsches Zentrum Fr Luft Und Raumfahrt E.v
Address
Linder Hoehe, 51147 KOELN, Germany
Organisation website
EU Contribution
€0
Organisation
Ingenieria Y Economía Del Transporte S.a.
Address
Paseo Habana 138, 28036 MADRID, Spain
Organisation website
EU Contribution
€0
Organisation
Thales Atm
Address
19, rue de la Fontaine, BAGNEUX, France
Organisation website
EU Contribution
€0
Organisation
Ingeniera De Sistemas Para La Defensa De Espana Sa
Address
Edison, 4, 28028 MADRID, Spain
Organisation website
EU Contribution
€0
Organisation
Entidad Pública Empresarial Aeropuertos Españoles Y Navegación Aérea
Address
Arturo Soria 109, 28043 Madrid, Spain
Organisation website
EU Contribution
€0
Organisation
Eurocopter Deutschland
Address
Willy Messerschmitt Str. 1, 81663 MÜNCHEN, Germany
Organisation website
EU Contribution
€0
Organisation
Office National D' Etudes Et De Recherches Aérospatiales
Address
29, avenue de la Division Leclerc, BP72 CHÂTILLON CEDEX, France
Organisation website
EU Contribution
€0
Organisation
Agusta S.p.a.
Address
Via Giovanni Agusta 520, 21017 SAMARATE VARESE, Italy
Organisation website
EU Contribution
€0
Organisation
Sociedad Estatal Para Las Ensenanzas Aeoronauticas Civiles Sa
Address
Avenida de la Hispanidad, 12, MADRID, Spain
EU Contribution
€0
Organisation
Luchtverkeersleiding Nederland
Address
Stationsplein ZuidWest 1001, 75200 SCHIPHOL-OOST, Netherlands
Organisation website
EU Contribution
€0
Organisation
Gmv Aerospace And Defence S.a.
Address
Isaac Newton - P.T.M. 11, 28760 Tres Cantos - Madrid, Spain
Organisation website
EU Contribution
€0
Organisation
Sicta - Sistemi Innovativi Per Il Controllo Del Traffico Aereo
Address
Via Fulco Ruffo di Calabria c/o Aeroporto di Capodichino, NAPOLI, Italy
Organisation website
EU Contribution
€0
Organisation
Davidson Ltd.
Address
50 West Street, FARNHAM, United Kingdom
EU Contribution
€0
Organisation
Northrop Grumman Sperry Marine Bv
Address
118 Burlington Road, NEW MALDEN, United Kingdom
Organisation website
EU Contribution
€0
Organisation
Enav
Address
VIA SALARIA, 16, 138 ROME, Italy
Organisation website
EU Contribution
€0
Organisation
Thales Air Systems S.a.
Address
3 Avenue Charles Lindbergh, 20351 RUNGIS, France
Organisation website
EU Contribution
€0
Organisation
Ge Aviation Systems Limited
Address
Cheltenham Road, Bishops Cleeve, CHELTENHAM, GL528SF, United Kingdom
Organisation website
EU Contribution
€0

Technologies

Contribute! Submit your project

Do you wish to submit a project or a programme? Head over to the Contribute page, login and follow the process!

Submit